  • Client:
  • Royal Borough of Kingston
  • Consultant:
  • The Keegans Group
  • Value:
  • £2,500,000
  • Duration:
  • 50 Weeks
  • Form of Contract:
  • JCT Standard Form of Contract 2007
  • Procurement Method:
  • Single Stage Competitive Tender
Castle Hill Primary Schoolcastle hill externalCastle Hill Primary SchoolCastle Hill Primary School ExternalCastle Hill Solar Panels

Overview

We were Principal Contractor in the delivery of this expansion of Castle Hill Primary School to create a 2FE all-through primary school. The new extension was required at the northern end of the site to provide accommodation for KS2 pupils.

This extension accommodates 8 new classrooms to replace temporary accommodation; a new library and ICT suite; a new kitchen/dining hall; a SENCO office and space for a Speech and Language Specialist; Improved staff and pupil toilets and additional playground space.

The new classroom building is single storey with a clerestory split pitched insulated standing seam sheet metal roof.
The new dining hall building is single storey with barn type facetted pitched tiles roof supported on glu-lam timber structure and traditional joisted flat roof to ancillary areas.

Sustainability Initiatives

The project has been designed as an exemplary low-energy project to meet the brief criteria of 60% reduction in CO2 emissions and BREEAM ‘Very Good’.

Key features include: classroom block orientated to minimise solar gain and maximise views over mature landscaping 180m2 photo-voltaic array mounted on the existing school roof excellent U-values - typically 0.15W/m2K for floors, walls & roofs natural ventilation & night purging via roof-mounted windcatchers solar control glazing to south & west elevations augmented with brise-soleil, low-eglazing to east & north elevations.  Smart controls to all lighting exposed thermal mass to regulate & minimise overheating.

Testimonials

I wanted you to know that both RBK and the School Community are absolutely delighted with the junior classrooms and the Dining Hall at Castle Hill. They are a credit to the work of Thomas Sinden and the whole project of the new works has been very successful.

Donald Farquharson - Head of Capital Programmes
Royal Borough of Kingston